St. Luke's reordering May update 2

Posted on the 22nd May 2019 at 6:24pm.

Floor tiling started Monday 20 May. Tiles around the font. None of the tiles are fixed yet. Ian, the tiler, is setting out the principle lines first. The most important principle line is the longitudinal one that is central on the chancel...

St. Luke's reordering May update

Posted on the 17th May 2019 at 8:38pm.

View into church. Pulpit being reinstalled. Font installed and protected. Font cleaned and in position. Cupboard hiding ufh manifold. The finished cupboard will be painted and have skirting around it. Main church cleared and ready for tiling to start. The church looks much taller without the...